Commissioning Walkthrough
A guided tour of commissioning (Cx) in Baler, from a new building's design phase through warranty, operations and maintenance, plus a retrofit and a campus of many small projects. It uses demo data you can create and remove with one script, so you can watch the data come online while you click through the Commissioning tab, the equipment tree and Alarms.
What commissioning is
Commissioning is a quality process, not a single test. ASHRAE Guideline 0 describes it running from pre-design through occupancy and operation, to verify the building meets the owner's requirements. Three documents anchor it:
- OPR (Owner's Project Requirements): measurable outcomes the owner wants.
- BOD (Basis of Design): how the design meets each OPR item.
- Cx Plan: written in pre-design, updated each phase.
New construction adds design and submittal review, start-up checklists, functional performance tests, an issues log, training, a final report and a Systems Manual. Warranty brings a review at about month 10 of a 12-month warranty, seasonal or deferred tests (peak summer, shoulder, peak winter) and an end-of-warranty report listing open deficiencies.
Retro-commissioning (RCx) is for existing buildings that usually have no OPR on file: start from as-found discovery (trends, a walkthrough), fix the low-cost items, and re-check. Savings from a one-time RCx tend to fade (a Berkeley Lab study cites roughly 35%), which is why monitoring-based commissioning keeps analytics running afterwards. Cost and savings figures in vendor material vary widely, so treat them as rough.
Sources: ASHRAE Guideline 0 overview, Newfoundland and Labrador commissioning guide, Kentucky commissioning plan outline, University of Maryland general commissioning requirements, ASHRAE retro-commissioning two-pager.
How Baler maps onto it
| Cx activity | Baler |
|---|---|
| Project and phases | A Cx project with an editable phase list (default: design, construction, start-up, functional, acceptance, warranty, operations; the demo adds maintenance) |
| Expected equipment and points | SHACL templates (ontology/cx-expected-points.ttl) checked against the Brick/Haystack model |
| Is it installed, alive, responding | The verification ladder: existence, liveness (trend data), responsiveness |
| Start-up and functional tests | Procedures (power-on, start-up, functional), including S1-S3 sequence criteria seeded from a spec's acceptance criteria |
| Sequence checks | Optional ASHRAE Guideline 36 items (gl36:* results) |
| Issues log | Cx issues opened from failing (or inconclusive) results. A passing run only resolves one (ready_for_retest, shown as "resolved, pending verification"); a later run over data from after the fix records the retest; only a person closes it, and the close cites that retest |
| Waivers | An accepted risk on an issue (reason, owner, retest trigger and review-by date, all required), so a known failure or an inconclusive result can be signed off. The accepter is named by the display name on their account (Ops -> Users), labelled CxA in the report when it matches settings.cxa_name |
| Phase sign-off | Phase gates: moving into start-up, functional testing and acceptance (and later) checks the records first (settings.phase_gates: warn, block or off) |
| Final report | The project Cx report, GET /cx/projects/{id}/report?format=html: phase history, spec vs installed, verdicts, procedure results, the issues log with who did what |
| Ongoing commissioning | Fault rules and derivations running on live data, shown in Alarms and Derivations |
What each gate checks, computed from the records rather than ticked:
| Moving into | Needs |
|---|---|
| Start-up | a completed verification run; every point reporting in it |
| Functional testing | the above, and every power-on / start-up procedure passing on its latest test run |
| Acceptance, warranty, operations | the above, every procedure passing with nothing inconclusive, no issue that isn't closed (a resolved issue still needs a person), and no inconclusive result in the latest run unless it is waived |
Moving back a phase is never gated. With block, an unmet gate answers 409
unless the move is overridden with a note, which the phase history records.
Preview a move with GET /cx/projects/{id}/gate?to=acceptance; the
Commissioning tab shows the same preview before you move.
Limits worth knowing:
- Apart from the gates, the phase you are in is recorded with each run but does not change what a run checks, and one run per project can be active at a time.
- The demo seeds no procedures and no spec, so its gates check runs and issues only, and its report says sequences of operation were not evaluated. Add a procedure (Procedures tab, or seed one from a spec) to see that part.
- Each demo project is scoped to its own equipment by topic prefix
(
settings.prefixes, Baler#75), for examplefbf/demo-cx/newbuild. A project without a prefix covers the whole organization. On a server that predates Baler#75 the prefix is saved but ignored, and every project reports on all equipment. - The gateway rate-limits each signed-in user. The seed script paces itself and stops at the first 429 instead of retrying, so it is safe to rerun after a short pause.
Seed the demo
Everything is created through the public gateway, so it needs only a login:
Code
Equipment keys live under fbf/demo-cx/..., names say DEMO, and fault
rules are called demo-cx-*. up is safe to run twice: each project
carries on from the phase it is in. Same --seed, same data. An operator
can run everything except cleanup, because deleting records and Cx
projects is admin-only; point history is kept by design. up takes several
minutes: it paces itself under the rate limit and waits about two minutes
per project for the retest window (below). Run cleanup on a server that
already has the demo before reseeding it: old point history stays and can
hide the planted defects.
The new build and the retrofit use blocking gates
(settings.phase_gates: "block"), so the script can only move them when
the records allow it, and it stops with the unmet rules if they don't. The
campus projects keep the default (warn).
Walkthrough: the new build
up takes Riverside Clinic to operations. Its phase history, issue events
and report show every step below. To watch it happen screen by screen
instead, run python -m scripts.seed_cx_demo advance newbuild between
steps on a fresh project. advance never closes an issue for you.
-
Design. The project exists and has no equipment. The plan is in place and nothing is built.
-
Construction. Equipment and points appear in the equipment tree (AHUs and VAV boxes with their Brick classes) but nothing has a value yet. The VAV boxes are installed without the damper-position and airflow points the template expects.
-
Start-up. First readings arrive (backdated a day) and a verification run checks them. The start-up gate needs that run, with every point reporting. The missing VAV points don't block it: they are a template gap, not a point that has stopped reporting. Open a point and its history chart starts to fill.
-
Functional testing. A day of trends lands with planted defects, and the 24-hour run fails 9 results under
fbf/demo-cx/newbuild:- the mixed-air sensor on
ahu-2hasn't reported in the window (stale); - the supply-air sensor on
ahu-2reads a constant 55 and the outside-air sensor onahu-1a constant 140. Liveness catches both as flat, and the equipment-levelladderresult fails with them; - each VAV box is missing its damper position and airflow points.
The script opens an issue for every failure (
POST /cx/runs/{id}/issues). A value that is merely out of range, rather than flat, is the fault rules' job:demo-cx-sat-rangeanddemo-cx-oat-rangearecur-mode rules, which judge readings as they arrive over MQTT. The seed posts its readings over HTTP, so those two never fire on demo data; thehis-modedemo-cx-stuckanddemo-cx-stalerules do (see the campus below). - the mixed-air sensor on
-
Acceptance. The issue rules (Baler#86) take three steps, and each one is recorded on the issue:
- Resolve. The contractor installs the missing VAV points and every
sensor reports healthy values. The next run passes those checks, which
moves each issue to resolved, pending verification
(
ready_for_retest, eventresolve.evidence). A passing run never closes an issue. - Retest. A second run whose whole window starts after the fix, so
it rests only on new data, passes again (event
retest.passed). A pass judged on data from before the fix doesn't count. If the check had failed instead, the issue would go back to open (retest.failed). - Close. A person closes each retested issue (Issues tab, or
PATCH /cx/issues/{id}with{"status": "closed"}), and the close cites the retest. The API refuses to close a check-tied issue that isn't resolved and retested. For the new build, the script closes them as the logged-in user, with a note saying so.
Only then is the acceptance gate met: a clean latest run, no inconclusive result without a waiver, and no issue left that isn't closed. The script runs a final acceptance run and moves the project.
- Resolve. The contractor installs the missing VAV points and every
sensor reports healthy values. The next run passes those checks, which
moves each issue to resolved, pending verification
(
-
Warranty. A 24-hour re-run, as the 10-month review would, and a place to record anything deferred.
-
Operations. The
demo-cx-*fault rules keep running. Watch Alarms for new faults (withliverunning, readings keep arriving). -
Maintenance.
advance newbuildadds the extra phase that marks steady-state work: acknowledge or snooze an alarm, and re-run on a schedule.
Then read the project report: python -m scripts.seed_cx_demo report newbuild saves GET /cx/projects/{id}/report?format=html as
cx-report-newbuild.html. It is a printable page with scope and
limitations, the phase history with each gate, spec vs installed, the
equipment verdicts from the latest run, procedure results, and the issues
log with every resolve, retest and close, who did it and when. The same
data comes back as JSON without ?format=html. The report needs the
Authorization header, so a plain browser link won't open it; use the
Commissioning page's Project Cx report button, the script, or
curl -H "Authorization: Bearer $TOKEN". Add &origin=https://your-baler
so the trend links in a saved copy point at your Baler (the button and the
script do).
Walkthrough: the retrofit and the campus
Harbor Office (retrofit) follows the same tools in a different order: start from what is already there, run to find the gaps (as-found), fix the records and sensors, then leave fault rules and derivations running as monitoring-based commissioning.
up leaves the retrofit in functional testing with its 9 issues resolved
and retested, waiting for a person to close them. That last step is yours:
- Preview the move (
GET /cx/projects/{id}/gate?to=acceptance, or the Commissioning tab). The gate listsno_open_issues: 9 issues not closed, because a resolved issue still needs a person to close it. - Try to move to acceptance. The blocking gate refuses with 409.
- Open each issue, read its retest, and close it.
- Run
python -m scripts.seed_cx_demo advance retrofit. It runs the acceptance run and the gate lets the project through.
Campus: 24 small projects sit at mixed phases, some with a stuck or stale sensor, so you can see how the project list, filters and concurrent runs behave when one organisation manages many buildings at once. Runs are queued and workers process them in the background.
Check it worked
- The equipment tree shows
DEMOAHUs and VAV boxes. They currently appear in their own "Air_Handling_Unit" and "Variable_Air_Volume_Box" groups, next to the older "AHU" and "VAV" groups (Baler#76). - The new build's functional-phase run has 9 failures (the VAV template, the stale mixed-air sensor, the two flat sensors and their ladder results). Its 9 issues show resolve, retest and close events, and every phase move in its history says the gate was met.
- The retrofit sits in functional testing with 9 issues resolved and retested, and its acceptance gate lists them until you close them.
report newbuildsaves a report that shows 0 issues not closed and every equipment passing.- Alarms lists open
demo-cx-stuckanddemo-cx-stalefaults on the campus buildings that were seeded with a stuck supply-air or stale mixed-air sensor. The new build and retrofit were fixed before you look, so they have none.livekeeps values fresh. cleanupremoves the records, rules and projects, anduprebuilds them.